Major road construction underway on Linden Rd.


Photo by Rhonda Sanders Photo by Rhonda Sanders FLINT TWP. — Road construction crews have rolled out the orange barrels to start nearly seven months of reconstruction work on Linden Road between Lennon and Calkins Roads. The project began Monday, April 17, and is targeted for completion on November 10. Motorists are advised to seek an alternate route or plan for delays while traveling Linden Road.

The project, now underway, will be broken into four stages. The first stage begins 700 feet south of Corunna Road and extends north to Calkins Road, according to a press release from the Genesee County Road Commission. Traffic will be maintained using the east side of Linden Road. The western leg of Court Street will also be under construction and will be closed to traffic. A detour sign will be posted.

The scope of the project includes to remove outside lanes; place new concrete pavement and curbs; rehabilitate inside lanes; rehabilitate the storm sewer system; remove and replace drive and road approaches; remove and replace Ryant Drain culverts and restripe pavement and place new signs.

This project is funded by a combination of federal and road commission matching funds. The estimated project cost is about $4.8 million. — Rhonda Sanders

Return to top

Copyright 2010-2017 The Flint Township View, All Rights Reserved

Click here for digital edition
2017-04-20 digital edition